Mental Health Phase 1
OWNER:
Department of Veteran Affairs
TYPE OF CONSTRUCTION:
New Construction
LOCATION:
Salisbury, NC
TOTAL AMOUNT:
$7,644,439.00
This project consisted of new vertical construction of a 25,000 sq ft Mental Health facility. The scope of work included:
- Extensive Site work (Demo, Grade and Infill 8,400 CY, Erosion Control)
- Underground Utilities (Demo and Replace Storm, Sanitary and Water lines)
- Auger Cast Piles (257) 16” diameter, 30’ deep
- Concrete, Forms and Rebar
- Masonry: 75,000 square foot new brick installation, 1,900 Precast panels
- Structural Steel (235 tons)
- Roofing: 23,600 sf. of EPDM
- Installed (108) Fixed and Side Hinged Exterior Dept. of Defense
- Blast Resistant windows.
- Stucco and EIFS: 3,500 square foot
- Finishes: Drywall and Metal Framing, Acoustical Ceiling, Flooring (Carpet, Ceramic, and Vinyl Sheet)
- Elevators (2 Passenger, 2 Service- 4 landings)
- HVAC and Plumbing (Extensive SOW)
- Electrical: (Extensive SOW: Generator, Transformers, Fire Alarm, Voice and Data, Security, CCTV)